![Renovation of the first floor area below the media center is now underway. Formerly classrooms, this area will become the lower level of the media center. A staircase will connect the two levels. Renovation of the first floor area below the media center is now underway. Formerly classrooms, this area will become the lower level of the media center. A staircase will connect the two levels.](/documents/download/?id=14137&forcedownload=0&thumbnail=1) |
Renovation of the first floor area below the media center is now underway. Formerly classrooms, this area will become the lower level of the media center. A staircase will connect the two levels. |
|
|
![Opening the ninth grade center by Jan. 5 allowed space on the first floor beneath the media center to be vacated. This area has been gutted and renovations will create a second floor to the media center. Opening the ninth grade center by Jan. 5 allowed space on the first floor beneath the media center to be vacated. This area has been gutted and renovations will create a second floor to the media center.](/documents/download/?id=14136&forcedownload=0&thumbnail=1) |
Opening the ninth grade center by Jan. 5 allowed space on the first floor beneath the media center to be vacated. This area has been gutted and renovations will create a second floor to the media center. |
|
|
![Work to complete classrooms in the ninth grade center was done over winter break. Work to complete classrooms in the ninth grade center was done over winter break.](/documents/download/?id=14134&forcedownload=0&thumbnail=1) |
Work to complete classrooms in the ninth grade center was done over winter break. |
|
|
![The exterior of the fieldhouse has been bricked. The addition will provide space for physical education classes. The exterior of the fieldhouse has been bricked. The addition will provide space for physical education classes.](/documents/download/?id=14140&forcedownload=0&thumbnail=1) |
The exterior of the fieldhouse has been bricked. The addition will provide space for physical education classes. |
|
|
![Inside the commons area, the terrazzo floor is installed and walls and ceiling are being completed. The commons is expected to open to student use in the coming weeks. Inside the commons area, the terrazzo floor is installed and walls and ceiling are being completed. The commons is expected to open to student use in the coming weeks.](/documents/download/?id=14139&forcedownload=0&thumbnail=1) |
Inside the commons area, the terrazzo floor is installed and walls and ceiling are being completed. The commons is expected to open to student use in the coming weeks. |
|
|
![The new commons / cafeteria space next to the ninth grade center has been enclosed and windows are installed. The new commons / cafeteria space next to the ninth grade center has been enclosed and windows are installed.](/documents/download/?id=14138&forcedownload=0&thumbnail=1) |
The new commons / cafeteria space next to the ninth grade center has been enclosed and windows are installed. |
| |
![On each floor, classrooms for core subjects surround resource areas, which have lockers and computers for students to use. On each floor, classrooms for core subjects surround resource areas, which have lockers and computers for students to use.](/documents/download/?id=14135&forcedownload=0&thumbnail=1) |
On each floor, classrooms for core subjects surround resource areas, which have lockers and computers for students to use. |
|
| | |
|